ROTTERDAM COURT
Place of session Rotterdam
Administrative Law
Case number: ROT 22/6060
and
(Agents: Mr. S.C. van Tuijl-Koese and Mr. D.C. Alblas).
1. In this ruling, the court reviews the plaintiff's appeal against the rejection of his application for an environmental permit to install a dormer on the front of his residence at [address] (hereinafter: the plot).
1.1.The college rejected this application with the decision of June 3, 2022 (hereinafter: the primary decision). With the contested decision of November 7, 2022 on the claimant's objection, the college stood by the rejection of the application.
1.2.The College responded to the appeal with a statement of defense.
1.3.The court heard the appeal at a hearing on September 5, 2024. Participating therein were: plaintiff and the agents of the college.
2. On January 1, 2024, the Environment Act and the Environment Act Implementation Act entered into force. If an application for an environmental permit was submitted before the time of entry into force of the Environment Act, pursuant to Section 4.3, opening sentences and under a, of the Environment Act Entry Act, the law as it applied immediately before that time will remain applicable until the decision on that application becomes irrevocable, with the exception of Section 3.9, third paragraph, first sentence, of the Environmental Law (General Provisions) Act (hereinafter: the Wabo).
The application for an environmental permit was submitted on March 25, 2022. This means that in this case the Wabo, as it applied before Jan. 1, 2024, continues to apply.
3. The court reviews the upholding of the denial of the environmental permit. It does so on the basis of the plaintiff's grounds of appeal.
4. The court finds that the appeal is unfounded. Below, the court explains how it reached this judgment and the consequences of this judgment.
4.1.The laws and regulations important to the assessment of the appeal can be found in the appendix to this ruling.
What is the case about?
5. Plaintiff applied on March 25, 2022, to construct a dormer on the front of his home. Plaintiff has already completed the dormer.
5.1.The zoning plan "Dorpsgebied Stellendam en Havenhoofd 2011" (hereinafter: the plan regulations) applies. Pursuant to this, the zoning "Residential - 1" applies to the parcel as far as relevant. The parcel has the building indication "semi-detached" and a maximum gutter height of 4 meters applies.
5.2.The college refused the environmental permit because the building plan does not comply with the 2012 Building Code and reasonable standards of appearance.n
Section 2.10(1)(a) and (d) of the Wabo. Section 2.10(1)(c) of the Wabo. Article 18.2.1(a) of the plan rules. Section 2.12(1)(a)(2o) of the Wabo.
5.3.Claimant disagrees and has filed an appeal.
Was the environmental permit granted by operation of law?
6. Primarily, the plaintiff argues that the environmental permit was granted by operation of law because the college did not decide on its application in time. To this end, the plaintiff argues that the time limit to decide was not suspended because additional information was not requested. This entails that the decision period has passed. Furthermore, the claimant argues that he was not sent the primary decision by mail, but rather wrongfully via e-mail, while he did not give his consent to do so (Article 2:14, first paragraph, of the General Administrative Law Act (Awb)). Therefore, the decision was not published in the prescribed manner, so that publication did not take place until after the decision period. Since the environmental permit was granted by operation of law, according to the plaintiff, the Board erred in failing to publish this environmental permit.
6.1.The College takes the position that the environmental permit was not granted by operation of law. First, according to the college, the decision period was validly suspended, so that a decision was made within the decision period. In the primary phase, the plaintiff was represented by an agent. It follows from the procedural documents that communication took place both with the claimant's agent and with the claimant. Moreover, the plaintiff submitted the application digitally via the Environment Counter (OLO), so that the decisions were also sent digitally. Several times during the procedure, the application was communicated electronically. Thereby, the plaintiff has made it known that it can be sufficiently reached by electronic means.
6.2.Although Section 4.3 of the Enabling Act for the Environment Act expressly excludes Section 4.1.3.3 of the Awb, which deals with the positive fictitious decision in the event of an untimely decision, from the moment of entry into force of the Environment Act, the moment, if any, at which the environmental permit was granted by operation of law in this case is prior to the entry into force of the Environment Act. After all, the decision period in these proceedings ended before January 1, 2024, so that pursuant to the Wabo, if this period is exceeded, the requested environmental permit was granted by operation of law. This means that the court will give an opinion as to whether the environmental permit came into being by operation of law.
Itis not disputed between the parties that, whether or not the building plan is in conflict with the zoning plan, the regular preparation procedure applies in any case. Either the building plan is not in conflict with the zoning plan, or if it is, Section 2.12, subsection 1 opening words and under 2o of the Wabo, read in conjunction with Section 4 opening words and part 1 of Annex II of the Environmental Law Decree (hereinafter referred to as: the Bor) gives the authority to grant an environmental permit for the building plan.
6.4.Pursuant to Section 4:20b, first paragraph, of the Awb, if a decision on the application for a decision is not made in time, the requested decision is made by operation of law. Pursuant to Section 3.9(1) of the Wabo, the competent authority shall decide on the application for an environmental permit within eight weeks from the date of receipt of the application. Under the second paragraph, the competent authority may extend this period once by a maximum of six weeks. The plaintiff, through his authorized representative, submitted the application digitally through the Environment Desk online on March 25, 2022, and the college thus received the application that day. The action of an agent (Article 2:1 of the Awb) has the effect that contact with the interested party is in principle through the agent. This also entails the principle of due care. With the letter and by e-mail dated April 14, 2022, the college requested additional information from the claimant's authorized representative, as referred to in Article 4:5 of the Awb. The court does not follow plaintiff's contention that college improperly requested the additional data requested. The college was reasonably entitled to do so. Pursuant to 4:15(1)(a) of the Awb, the decision period is therefore suspended from the day after that on which the college invites the applicant to supplement the application pursuant to 4:5 of the Awb, until the day on which the application has been supplemented or the period set for that purpose has expired unused. The college received additional information on May 13, 2022. By email dated May 16, 2022, the plaintiff's authorized representative indicated that, if requested, the plaintiff did not agree to narrow the dormer to three meters. The authorized representative additionally included the spatial justification for the building standards committee. The college subsequently indicated by email that the spatial substantiation had already been submitted to the building standards committee and that it did not agree. From March 26, 2022 (the day after receiving the application) to April 14, 2022, 20 days of the decision period elapsed. Subsequently, this deadline was suspended until May 13, 2022. From May 13, 2022 (the day the application was completed), the remaining period of 36 days began to run. The college made a timely decision with the June 3, 2022 decision.
6.5.Pursuant to Article 3:40 of the Awb, a decision shall not take effect until it has been published. Pursuant to Article 3:41, first paragraph, of the Awb, publication of decisions addressed to one or more interested parties shall be made by sending or delivering them. Pursuant to Article 2:14, first paragraph, of the Awb, an administrative body may send a message addressed to one or more addressees electronically to the extent that the addressee has made it known that it can be sufficiently reached by this means. The judgment of the Administrative Law Division of the Council of State (hereinafter: the Division) of October 26, 2022, ECLI:NL:RVS:2022:3088 states that it follows from the history of the creation of Article 2:14, first paragraph, of the Awb that "in order to be allowed to send a message electronically, it is required that the addressee has made it known that he can be sufficiently reached by that means. The legal text does not impose any requirements on the manner of notification. Disclosure may be more or less explicit. The addressee will have to indicate at which electronic mail address he can be reached. [...]" It can be inferred from the foregoing that the making known within the meaning of Article 2:14 of the Awb can be done both implicitly and explicitly. Although the explanatory memorandum does state that "for the time being" explicit notification must still be assumed, that text dates from more than fifteen years ago and since then electronic communication with the government has developed considerably. No decisive significance is therefore attached to that text.
6.6.The primary decision was sent and received both to Claimant's agent and Claimant himself by email dated June 3, 2022. It does not follow from the documents that an express request was made to receive the decision by mail. Nor was it made known that the agent did not wish to receive the decision by email. In view of the foregoing and the subsequent e-mail traffic between the authorized representative and the licensing authority, the plaintiff did not make it clear that he could not be reached electronically. As a result, the college correctly published the decision, so that it took effect.
6.7.In view of what has been considered above, the court finds that the environmental permit did not arise by operation of law because the decision to refuse the environmental permit was published in a timely and proper manner. Therefore, there was no reason for the college to publish an environmental permit granted by operation of law. This ground for appeal does not succeed. This means that the court will further address the substantive grounds of the appeal below.
Review framework
7. Under Section 2.1, first paragraph, under a, of the Wabo, it is prohibited to build a structure without an environmental permit. Pursuant to Section 2.10, first paragraph, of the Wabo, the environmental permit is granted if there is no conflict with the 2012 Building Decree, the building regulations, the zoning plan and the reasonable requirements of the neighborhood. Pursuant to the second paragraph, if there is a conflict with the zoning plan, the application is also considered to be an application for the activity of use in conflict with the zoning plan, as referred to in Section 2.1, first paragraph, under c, of the Wabo.
7.1.It is not in dispute between the parties that the dormer is not completely permit-free for the activity of building and use in conflict with the zoning plan pursuant to Article 2, Annex II, of the Bor.
Does the building plan violate the zoning plan?
8. The plaintiff argues that the building plan does not conflict with article 18.2.1, under e, of the plan regulations, because the building of the dormer does not exceed the gutter height. Pursuant to Article 2.6 of the plan rules, the gutter height is measured from the ground level up to the top of the gutter/drip line, the fascia board or an equivalent construction part. In a Division decision of August 28, 2019, ECLI:NL:RVS:2019:2879, r.o. 2.2, the Division ruled with regard to the same definition that the planning legislator did not consider the place where the gutter is installed to be decisive for the gutter height, but the place where the water drips from or where a fascia board or similar structural part is installed. According to the plaintiff, the roof of his home drains at the top, bottom, and both sides, so rainwater is drained through the existing gutter and not through the dormer. Because there is no conflict with Article 18.2.1(e) of the plan rules, according to the plaintiff, an assessment of Article 18.2.1(i) of the plan rules is also out of the question, so that the board has also wrongly tested against it, the plaintiff said.
8.1.Pursuant to Article 18.2.1(e) of the planning regulations, the gutter height of main buildings shall not exceed the indicated gutter height. On the site of the plot, the maximum gutter height is 4 meters. Pursuant to article 2.6 of the plan rules, the gutter height is measured from the ground level up to the top of the gutter / drip line, the fascia board or an equivalent construction part. The court ruled, in line with the decisions of the Division, that this means that the planning legislator did not only consider the place where the gutter is installed to be decisive for the gutter height, but also the place where the water drips from or where a fascia board or similar structural part is installed. On the drawings accompanying the application, the dormer is 6.25 meters wide and provided on both sides only 0.5 meters from the side walls, so that the dormer occupies almost the entire roof surface in width. In addition, the dormer runs almost flush with the ridge at the top, so water must be drained from the top of the dormer. It follows from the detailed drawing that there is a gutter on the side of the dormer from which the water drips. In view of the foregoing, the court follows the board's position that, in view of the definition in the plan rules, the top of the dormer here determines where the gutter height is located. Each building plan must be assessed on its own merits. The situation in the ruling cited by the plaintiff is not entirely comparable to the present building plan, so that this cannot benefit the plaintiff. In view of this, the court finds that the building plan exceeds the maximum gutter height prescribed in the zoning plan.
Pursuant to Article 18.2.1, under i, of the plan rules, if the gutter height is exceeded, a dormer is possible if the dimensions described in that article are met. This concerns the following points: the distance to the eaves, the ridge and the sides of the roof plane is at least 0.5 m, the building height of the dormer, measured from the base of the dormer, is at most 1.75 m, the width of dormers at the front or side of the main building is at most 50% of the roof plane. Given the drawings accompanying the application, the distance requirement of 0.5 meters from the ridge is not met. Furthermore, the width of the dormer is not at most 50% of the roof plane.
8.3.This means that the Board was right to also classify the application as an application for the activity of use contrary to the zoning plan, as referred to in Article 2.1, first paragraph, under c, of the Wabo.
Could the college reasonably refuse to deviate from the zoning plan?
9. It is established case law of the Division (see inter alia the judgment of September 4, 2024, ECLI:NL:RVS:2024:3584) that, in deciding whether or not to apply the authority granted to it to grant an environmental permit in derogation of the zoning plan, the Municipal Executive is entitled to policy discretion and must weigh the interests involved. The administrative judge does not himself decide whether granting the environmental permit is in accordance with good spatial planning. Based on the grounds for appeal, the administrative judge assesses whether the decision is in accordance with the law. This may include whether the adverse consequences of the decision are disproportionate in relation to the objectives to be served by granting the environmental permit.
9.1.The college does not want to cooperate with the plan, because such an expansion always detracts from the spatial quality. At the hearing, the college explained that this relates in particular to a front dormer wider than 50% of the roof area. The plaintiff has rightly noted that in the Policy Rule on Deviation Policy for Spatial Planning 2015 under 3.4 reference is still made to the Goeree-Overflakkee 2015 Welstandsnota. This static reference is outdated because, at the time of interest, the new Welstandsnota Nota Ruimtelijke Kwaliteit 2016 had now come into effect. However, this cannot help the plaintiff, because the college interpreted the policy rule in such a way that they considered it to be a reference to the new building standards memorandum and the building standards policy had not been changed as far as relevant here. Regarding the height, the college explained that it does want to deviate from the plan rules insofar as the dormer is flush with the dormer of the adjacent property. However, the width of the dormer envisaged in the application is still too far-reaching a deviation from the zoning plan, since instead of the prescribed maximum width of 50% of the roof surface, it concerns a dormer over almost the entire width of the roof surface. That, as explained at the hearing, is in no way a subordinate building component on the roof plane in terms of dimensions. In what the claimant has argued the court, given the policy space available to the college, sees no ground for the opinion that the college could not reasonably take the position that the building plan is in conflict with good spatial planning. The adverse consequences for the claimant of refusing to cooperate with the building plan to that extent have been sufficiently considered by the college in the decision-making process. The issue of whether there are still possibilities to modify the building plan was discussed at the hearing. The college has indicated that this is problematic because the claimant has already realized the dormer. The college considers the requested dormer too wide anyway. The plaintiff has indicated an unwillingness to adjust the width, so there is no room for an adjustment that could possibly be permitted in deviation from the zoning plan.
Is the dormer for the activity of "building" permit-free?
10. The plaintiff argues that the dormer is permit-free for the construction activity because the dormer is located more than 0.5 meters below the roof ridge, thus complying with Article 3, opening words, part 3 of Annex II of the Bor.
10.1.Under Section 2.1, first paragraph, opening words, under a, of the Wabo, it is prohibited to build a structure without an environmental permit. However, under Section 3, opening words, part 3, of Annex II of the Bor, an environmental permit for the activity of building is not required if this activity concerns a dormer in the front roof plane, provided that the following requirements are met:
reasonable welfare requirements are not applicable;
fitted with a flat roof,
measured from the base of the dormer not higher than 1.75 m,
underside more than 0.5 m and less than 1 m above the eaves,
top more than 0.5 m below the roof ridge, and
sides more than 0.5 m from the sides of the roof plane; [...].
10.2.It follows from the construction drawings that the claim that the dormer is located more than 0.5 meters below the roof ridge is not plausible. In addition, the other conditions must also be met. For example, the reasonable requirements of aesthetics must also not be applicable. It is not in dispute that the reasonable requirements of prosperity do apply here, so that the activity is not permit-free on this basis either. This means that the claimant needs an environmental permit for the activity of building, whereby the assessment framework in Section 2.10(1) of the Wabo applies. In view of that assessment framework for the activity of building, the building plan must also comply with the Building Decree 2012n
Section 2.10(1)(b) of the Wabo
10.3.This ground of appeal does not succeed.
Reasonable standards of welfare
11. The plaintiff argues that the building plan does not violate reasonable building standards. The building plan opinion wrongly addresses dimensions already given in the zoning plan. The advice should not interfere with the building regulations of the zoning plan. The plaintiff refers to a Division ruling of January 18, 2017, ECLI:NL:RVS:2017:88, r.o. 4.2. Therefore, the Board has not fulfilled its duty of discernment (ECLI:NL:RVS:2018:4049, r.o. 5.2).
11.1.The aesthetics advice dated April 12, 2022 states that the plan is contrary to reasonable requirements of aesthetics, unless the width is limited to 3 meters, in accordance with the aesthetics note. As far as the distance to the ridge is concerned, the plan can be deviated from, provided the height of the adjacent dormer is maintained.
11.2.It is established case law that the building standards test must, in principle, focus on the building possibilities offered by the zoning plan in force. It follows from the general nature of the building standard requirement that the building possibilities applicable to the land must be used as the starting point in the building standard test.
11.3.As considered under 8.1, the circumstance that the application complies with the dimensions of Article 18.2.1 of the planning regulations does not arise because the dormer is 6.25 meters wide. With this dimension, the maximum width of 50% of the roof plane is not met. To that extent, the building plan already does not comply with the maximum construction possibilities of the zoning plan. Therefore, to that extent, the question raised by the plaintiff as to whether the building plan opinion interferes with the building possibilities of the zoning plan is also irrelevant here. However, this does not alter the fact that if the claimant submits an application whereby the dormer is 3.625 meters wide (50% of the total roof area of 7.25 meters), the college will have to consider whether the building regulations of the building stand policy, in which the dormer may be a maximum of 3 meters, interferes with the planning regulations.
11.4Although the Municipal Executive is not bound by a recommendation on building standards and the responsibility for building standards assessment lies with the Municipal Executive itself, it may rely on that recommendation, after checking whether it has been drawn up in a careful manner, the reasoning in it is comprehensible and the conclusions drawn are consistent with it. This obligation is laid down in article 3:9 of the Awb for the legal advisor and follows from article 3:2 of the Awb for other advisors. In principle, the adoption of a welfare recommendation does not require further explanation. This is different if the applicant or a third interested party has submitted an opinion from another person or body deemed to be competent, or has brought forward concrete indications for doubts about the care with which the opinion was drawn up, the comprehensibility of the reasoning followed in the opinion or the consistency of the conclusions with it.
It is not in dispute that the building plan is contrary to the requirements laid down in the Nota Ruimtelijke Kwaliteit 2016 building standards memorandum. The claimant must be credited with the summary nature of the building standards advice. On the other hand, with reference to paragraph 2.3.6. of the building standards memorandum, the determination that the building plan does not fit into the building standards rules that apply to the construction of a dormer is in itself clear enough. Thereby the advice of the building standards committee sufficiently shows that and why the building plan is considered to be in conflict with the reasonable requirements of building standards. In what the claimant has argued, the court sees no ground for the opinion that the college could not adopt the building standards recommendation without further explanation. In view of the foregoing, the Municipal Executive was able to take the position that the building plan was in conflict with reasonable requirements for building standards, so that to that extent it was justified in assuming that a ground for refusal existed that prevented the granting of an environmental permit.
Building Code 2012
12. The plaintiff argues that there is no violation of the 2012 Building Code. The motivation in the primary decision was insufficient. The inconsistency mentioned in the contested decision with regard to the insulation value came out of the blue for the plaintiff and, moreover, is incorrect. Additional information was also never requested. The contractor does nothing but build dormers.
12.1.The college requested additional information with the letter dated April 14, 2022. The letter also stated that the plan does not comply with the 2012 Building Code. The Rc values of the dormer do not comply with sections 5.6 and 5.3 of the 2012 Building Code. The plaintiff has been given the opportunity to amend the plan. Claimant's claim that he was never asked for additional information cannot be followed given the letter dated April 14, 2022. The letter was sent to his agent, of which it has already been considered in recital 6.4 that the effect of acting as an agent (Article 2:1 of the Awb) is that, in principle, contact with the interested party goes through the agent. In the contested decision, reasons were given for not complying with Section 5.3 of the 2012 Building Decree. The thermal resistance of the vertical exterior partition construction with 4.5 m2 K/W does not meet the required 4.7 m2 K/W and the thermal resistance of a horizontal exterior partition construction with a value of 6.0 m2 K/W does not meet the required 6.3 m2 K/W. To the extent that the plaintiff brought up at the hearing that he could have solved this with drywall, he should have made this known at the time of the application. In view of this, the court is of the opinion that, based on the information and documents available with the application, the board could deem it plausible that the building plan violates the 2012 Building Code. The fact that the contractor does nothing but build dormers does not mean that the dormers always comply with the 2012 Building Code. In view of the foregoing, the Board was correct in assuming that, to that extent, a ground for refusal exists that prevents the granting of an environmental permit. This ground for appeal therefore does not succeed.
Equality principle
13. The plaintiff states that similar dormers have been built in the surrounding area. He pointed this out to the college in his spatial substantiation accompanying his application. According to the claimant, the fact that the permit was refused violates the principle of equality.
13.1.The Claimant merely submitted photographs without naming specific addresses. It is established case law of the Division that merely submitting photos of the cases the claimant is relying on, without naming addresses, is insufficient for a successful reliance on the principle of equality (see the Division's decision of 25 July 2007, ECLI:NL:RVS:2007:BB0391). In view of this, the Board was able to take the position that no equal or comparable cases were put forward that had to be included in the assessment. Also after the expiration of the appeal term and, if that term has been given, after the expiration of the term referred to in Article 6:6 of the Awb, in view of Article 8:58 of the Awb, new arguments may be put forward and documents, in order to substantiate a previous appeal, may be submitted, unless this is contrary to a good procedural order. This means that an appeal to the principle of equality made in the objection or appeal may be substantiated at a later point in the proceedings by citing concrete equal cases. In this case, the plaintiff did so only at the hearing. That is contrary to due process because the college can no longer adequately respond to it. The foregoing means that the court sees no ground in what the claimant has submitted for the opinion that the college has decided in violation of the principle of equality. This ground for appeal does not succeed.
14. The appeal is unfounded. This means that plaintiff is not vindicated. Therefore, plaintiff does not receive a refund of the court fee. Nor will he be reimbursed for his legal costs.
The court declares the appeal unfounded.
This judgment was pronounced by Mr. V. van Dorst, judge, in the presence of Mr. A. Regenboog, registrar. The judgment was pronounced in public on September 16, 2024.
The judge was prevented from signing the ruling.
registrar |
right |
A copy of this ruling was sent to the parties on:
A party who disagrees with this ruling may send a notice of appeal to the Administrative Law Division of the Council of State explaining why this party disagrees with this ruling. The notice of appeal must be filed within six weeks of the day this ruling was sent. If the petitioner cannot wait for the hearing of the appeal because the case is urgent, then the petitioner may ask the Interim Injunction Judge of the Administrative Law Division of the Council of State to grant a preliminary injunction (a temporary measure).
General administrative law
1. An administrative body may send a message addressed to one or more addressees electronically to the extent that the addressee has made it known that he can be adequately reached by this means.
[...].
1. The governing body may decide not to process the application if:
[...], or
[...], or
the information and documents provided are insufficient for assessing the application or preparing the decision,
provided that the applicant has had an opportunity to supplement the application within a time limit set by the governing body.
1. The period for issuing a decision shall be suspended as of the day following that on which the administrative body:
a. invites the applicant under Article 4:5 to complete the application, until the day on which the application is completed or the time limit set for it has expired unused, or
[...].
[...].
The governing body shall publish the decision within two weeks after it is issued by operation of law.
The publication and communication of the decision shall state that the decision is made by operation of law.
If the administrative body has not published the decision in accordance with Article 4:20c within two weeks, after a subsequent notice of default by the applicant, it shall forfeit a penalty from the day on which two weeks have elapsed since that notice of default.
The penalty shall be calculated in accordance with Article 4:17, paragraphs 1 and 2.
Articles 4:17(4) and (6)(a) and (b) and 4:18 to 4:20 shall apply mutatis mutandis.
Environmental Law (General Provisions) Act
1. It is prohibited without an environmental permit to carry out a project to the extent that it consists in whole or in part of:
a. building a structure,
b. [...],
c. the use of land or structures contrary to a zoning plan, a management ordinance, an exploitation plan, the rules laid down pursuant to Section 4.1(3) or 4.3(3) of the Spatial Planning Act, or a preparatory decision insofar as Section 3.7(4), second sentence, of that Act has been applied,
[...].
1. Insofar as the application concerns an activity as referred to in Article 2.1, first paragraph, under a, the environmental permit will be refused if:
the application and the information and documents provided with it do not, in the opinion of the competent authority, make it plausible that the construction of a structure to which the application relates complies with the regulations imposed by or pursuant to a general order in council as referred to in Section 2 or 120 of the Housing Act;
the application and the information and documents provided with it do not, in the opinion of the competent authority, make it plausible that the building of a structure to which the application relates complies with the regulations laid down by the Building Ordinance or, as long as the Building Ordinance has not yet been brought into conformity therewith, with the regulations laid down by an order in council as referred to in Section 8, eighth paragraph, of the Housing Act or by or pursuant to an order in council as referred to in Section 120 of that Act;
the activity is contrary to the zoning plan, the management ordinance or the exploitation plan, or the rules made pursuant to Article 4.1(3) or 4.3(3) of the Spatial Planning Act, unless the activity is not contrary to an environmental permit granted pursuant to Article 2.12;
the appearance or placement of the structure that is the subject of the application, with the exception of a temporary structure that is not a seasonal structure, both in itself and in relation to its surroundings or its foreseeable development, is contrary to reasonable requirements of prosperity, judged according to the criteria referred to in Article 12a, first paragraph, under a, of the Housing Act, unless the competent authority is of the opinion that the environmental permit should nevertheless be granted;
[...].
2. In cases as referred to in the first paragraph, under c, the application shall also be considered an application for a permit for an activity as referred to in Article 2.1, first paragraph, under c, and the permit shall be refused on the ground referred to in the first paragraph, under c, only if the granting of a permit pursuant to Article 2.12 is not possible.
1. Insofar as the application relates to an activity as referred to in Article 2.1, first paragraph, under c, the environmental permit may only be granted if the activity is not contrary to good spatial planning and:
a. if the activity is contrary to the zoning or management regulations:
[...],
2°. in cases designated by order in council, or
[...].
Environmental Law Decree
An environmental permit for an activity referred to in Section 2.1(1)(a) of the Act is not required if the activity concerns:
[...];
3. a dormer in the front roof plane, a side roof plane facing a publicly accessible area, or, insofar as it concerns a structure referred to in Article 2, Section 4(f), the rear roof plane, provided the following requirements are met:
reasonable welfare requirements are not applicable;
fitted with a flat roof,
measured from the base of the dormer not higher than 1.75 m,
underside more than 0.5 m and less than 1 m above the eaves,
top more than 0.5 m below the roof ridge, and
sides more than 0.5 m from the sides of the roof plane;
[...].
Zoning plan village area Stellendam and Havenhoofd 2011
[...].
gutter height of a structure
from ground level to the top of the gutter/drip line, fascia board or an equivalent structural member.
[...].
Destination Description
The land designated for 'Residential - 1' is intended for:
a. residential including home-related occupations and small-scale business activities;
[...].
Building Rules
Construction is permitted on these lands and the following rules apply:
Main buildings
[...];
the gutter height of main buildings shall not exceed the gutter height indicated by the indication 'maximum gutter height (m)';
[...];
i. at the location of the designations "detached," "two-by-one" and "attached" the gutter height of main buildings may be exceeded by dormers, if:
the distance from the eaves, ridge and sides of the roof plane is at least 0.5 m;
the building height of the dormer, measured from the base of the dormer, shall not exceed 1.75 m;
the width of dormers on the front or side of the main building does not exceed 50% of the roof plane;
the width of dormers at the rear of the main building does not exceed 70% of the roof plane.